Wi-Fi Extension Project

On 28th October 2013, the University approved a capital project costing almost £1 million to extend Wi-Fi coverage to all buildings at the Whiteknights campus, to renew the Greenlands campus Wi-Fi, and to extend coverage at London Road.

This page gives a brief overview of the deployment plan and status for each building. Please note the dates shown are estimated and are subject to change.

Completed - Completed Work in progress - Work in progress
Estimated start date Estimated completion date Status
Henley Business School Greenlands 11 November 2013 13 December 2013 Completed
Whiteknights Library 14 November 2013 02 December 2013 Completed
Maths (ground floor) 19 November 2013 21 November 2013 Completed
Palmer Building 21 November 2013 06 December 2013 Completed
HumSS Building 26 November 2013 10 January 2014 Completed
Henley Business School Whiteknights 16 December 2013 24 January 2014 Completed
ICMA Centre 02 January 2014 31 January 2014 Completed
Agriculture 08 January 2014 17 January 2014 Completed
Blandford Lodge 16 January 2014 31 January 2014 Completed
Maths (rest of building) 20 January 2014 24 January 2014 Completed
TOB 2 23 January 2014 31 January 2014 Completed
TOB 1 30 January 2014 07 February 2014 Completed
Harry Pitt 06 February 2014 14 February 2014 Completed
Meteorology 18 February 2014 20 February 2014 Completed
Park House Lodge 21 February 2014 21 February 2014 Completed
Whiteknights House 21 February 2014 24 February 2014 Completed
Systems Engineering 18 February 2014 26 February 2014 Completed
Carrington Building 14 March 2014 14 March 2014 Completed
Estates and Facilities 24 March 2014 26 March 2014 Completed
Old Whiteknights House 28 March 2014 01 April 2014 Completed
Wager Building 14 April 2014 24 April 2014 Completed
Cedars Hotel 06 May 2014 06 May 2014 Completed
Halls of Residence JCRs / Bars 14 May 2014 16 May 2014 Completed
JJ Thomson 28 February 2014 21 March 2014 Completed
Miller Building 17 March 2014 27 March 2014 Completed
Archaeology and Allen Lab 17 March 2014 27 March 2014 Completed
Minghella Building 19 March 2014 19 March 2014 Completed
Henley Business School Offices (formerly LRC) 24 March 2014 03 April 2014 Completed
Engineering 24 March 2014 03 April 2014 Completed
SportsPark 24 March 2014 03 April 2014 Completed
Earley Gate 31 March 2014 02 April 2014 Completed
Food Biosciences 01 April 2014 11 April 2014 Completed
Park House 01 April 2014 11 April 2014 Completed
Chemistry 03 April 2014 11 April 2014 Completed
Hopkins Building 07 April 2014 17 April 2014 Completed
Lyle Building 07 April 2014 17 April 2014 Completed
Harborne Building 14 April 2014 24 April 2014 Completed
Students' Union 14 April 2014 24 April 2014 Completed
AMS Tower 21 April 2014 30 April 2014 Completed
Knight Building 21 April 2014 30 April 2014 Completed
URS Building 28 April 2014 07 May 2014 Completed
Russell Building 28 April 2014 07 May 2014 Completed
Foxhill House 12 May 2014 23 May 2014 Completed
London Road Old Library 12 May 2014 23 May 2014 Completed
Great Hall 12 May 2014 23 May 2014 Work in progress
Museum of English Rural Life 27 May 2014 06 June 2014 Work in progress